10 Key Steps For Roller Screen Installation & Commissioning

Jan 24, 2026

In industrial production such as mining, coal, and building materials, our Roller Screens are the core equipment for material screening. The stability of their operation directly affects the production capacity and efficiency of the entire production line. And installation and commissioning, as the key pre-step for the equipment to be put into use, not only directly determines whether the equipment can achieve a ≥90% screening efficiency and a ≥10-year lifespan for the screen shaft, but also helps avoid more than 80% of the equipment operation failures in the future.

In fact, most problems such as decreased screening efficiency, premature wear of components, and abnormal operation sounds that occur with Disc Screens are not caused by the quality of the equipment itself, but by improper operation during installation and commissioning - hidden risks such as uneven foundation, deviation in concentricity, and inadequate lubrication will gradually intensify over time, increasing the subsequent maintenance costs. Therefore, we have sorted out a standardized 10-step installation and commissioning process covering the entire process from preparation to acceptance, to help everyone avoid pitfalls precisely and enable roller screens to quickly enter the optimal operating state.

 

Roller Screen Installation Commissioning

 

Preparations Before Installation And Commissioning

 Technical Preparation

  • Study Technical Materials: We will arrange for the technical team to communicate with the customer in advance, guiding them to carefully read the equipment assembly drawing, installation manual and electrical schematic diagram, clarifying key parameters such as the installation type (left or right installation, based on the direction of the coal flow), foundation dimensions, and sieve shaft spacing.
  • Develop a Special Plan: Based on the customer's on-site conditions (such as altitude and environmental temperature), we will assist in formulating the lifting plan, personnel division table and safety protection measures, clearly defining the responsible persons and timeframes for each link, ensuring that the installation work proceeds smoothly.

 

 On-Site Preparation And Material Preparation

  • Clean The Installation Site:We will remind the customer to ensure that the installation area has sufficient space to meet the requirements for equipment hoisting and subsequent maintenance. At the same time, we will remove dust, water accumulation and other interfering factors on the site to ensure operational safety.
  • Verify Equipment And Accessories: After the equipment arrives at the site, we will guide the customer to open the box and check whether the main body of the Wobbler Feeder, the sieve shaft, the motor, the reducer, the sealing parts, the high-strength bolts and other accessories are complete. Check for any transportation damage to the appearance and whether the dimensions of the key components comply with the drawing requirements. Ensure that there are no missing or damaged accessories.
  • Prepare Special Tools: We will inform the customer in advance of the list of required special tools and guide everyone to prepare tools and consumables such as lifting equipment (matching the weight of the equipment), level gauge, torque wrench, infrared thermometer, feeler gauge, and specified types of lubricating oil (grease) in advance to avoid delays in the project due to the lack of tools.

 

 Foundation Inspection

  • Verify Foundation Quality:We will assist the client in confirming that the embedded parts (steel structure) are positioned and sized as per the design drawings, with a smooth surface free of cracks or concrete looseness. Ensure that the foundation can bear the operating load of the equipment.
  • Check Levelness:Use a level gauge to measure the levelness of the foundation surface. The error should be controlled within ≤5mm/m. If it does not meet the standard, we will guide the client to level it using shims to avoid vibration caused by the foundation tilting during equipment operation, which could affect the equipment's lifespan.

 

10 Key Steps For Roller Screen Installation & Commissioning

 Step 1: Equipment Hoisting And Positioning

  • Prioritize Overall Hoisting:When our roller screen complete machine is shipped, we recommend that customers hoist it directly as a whole to reduce assembly errors on site. If installation conditions restrict the hoisting to separate parts, we will mark the positions of each component in advance and guide customers to assemble precisely to avoid misalignment.
  • Standardize Hoisting Operations: We will emphasize that the equipment's preset hoisting holes or hooks must be used for hoisting. During hoisting, keep the equipment level and prohibit anyone from standing below. When the equipment is lowered to the foundation, do so gently and slowly to avoid collisions that may cause the box to deform or the screen shaft to shift, resulting in irreversible damage.

 

 Step 2: Leveling And Alignment

  • Adjusting Levelness: We will guide the customer to use a level gauge to separately measure the longitudinal and lateral levelness of the equipment. By adding or removing spacer plates between the foundation and the base, we will make adjustments until the error meets the standards. This is the core prerequisite for the equipment to run smoothly.
  • Aligning The Center Position:Ensure that the center of the Wobbler Screen is exactly the same as the center of the foundation. At the same time, we will assist in checking the parallelism of the screen shaft, the concentricity between the output shaft of the reducer and the screen shaft, and the deviation should be controlled within ≤5mm. This is to avoid abnormal noises and additional wear during operation, and to extend the lifespan of the transmission components.

 

 Step 3: Fixation And Reinforcement

  • Tightening Connection Components: We will advise the customer to weld the equipment base firmly to the pre-installed parts (steel structure), or use high-strength bolts for fixation. The tightening torque of the bolts must be carried out strictly in accordance with the requirements provided by us to avoid loosening due to running vibration, which could lead to safety hazards.
  • Installing Shock Absorption Measures:Based on the vibration conditions at the customer's site, we will suggest adding shock absorption pads between the base and the foundation to reduce the dynamic load on the foundation during equipment operation, and at the same time reduce the wear of components caused by vibration, thereby improving the stability of equipment operation.

 

 Step 4: Electrical System Installation

  • Professional Wiring Operations:We will emphasize that the electrical wiring must be completed by certified electricians, following the electrical schematic diagrams provided by us to ensure secure and insulated connections, proper grounding resistance in line with safety standards, and to prevent leakage risks, thereby safeguarding the safety of personnel on site.
  • Control Function Testing:After installing the local explosion-proof operation box and the main control cabinet, we will guide the customer to test the start, stop, and emergency stop buttons, check whether the fault indicator lights and operation indicator lights are functioning properly, and simultaneously verify the interlock logic between the equipment and upstream and downstream equipment (such as crushers), ensuring it meets the production process requirements.

 

 Step 5: Sealing And Protection Inspection

  • Check The Sealing Devices: We will assist the customer in confirming that the labyrinth seals at the bearing ends, the sealing at the connection points of the box body, and the sealing devices at the inlet and outlet ports are installed properly. The sealing gaskets should be tightly attached without any looseness or gaps to prevent dust from entering the equipment and lubricating oil from leaking.
  • Strengthen Protective Facilities:We will remind the customer to check whether the protective covers and dust covers for the rotating parts are installed firmly to ensure there are no omissions. This will prevent personnel from accidentally touching during operation or dust from entering the equipment, thereby ensuring personnel safety and extending the equipment's service life.

 

 Step 6: Lubrication System Debugging

  • Select Appropriate Grease: We will clearly inform the customer that the motor bearings need to be filled with 3-grade general lithium-based grease. For the reducer, use N220 medium-load industrial gear oil in winter and N320 in summer. It is strictly prohibited to use grease of an incorrect model to avoid affecting the lubrication effect and causing damage to the components due to dry friction.
  • Inspect the Lubrication System:We will guide the customer to clear the lubrication pipeline to ensure smooth oil flow. The automatic lubrication system should be set according to our recommended parameters for the oil injection time and quantity. Check for no leakage in the pipeline, and ensure uniform oil supply at the lubrication points to guarantee effective lubrication of the core components.

 

 Step 7: Final Inspection Before No-Load Trial Operation

  • Mechanical part inspection:We will assist the customer in manually rotating the sieve shaft to ensure smooth rotation without any jamming or abnormal noise. Check that the gap between the sieve plates is uniform, the fasteners are not loose, the assembly of the sieve shaft and the sieve plates is in place, and to avoid mechanical failures after startup.
  • Electrical part inspection:Confirm that the power voltage is consistent with the equipment's marking, the motor rotation direction is correct (verified through point operation test), the signal transmission of sensors (temperature, vibration) is normal, there is no loose wiring, and ensure the reliability of the electrical system operation.

 

 Step 8: No-Load Test Run

  • Test Run Requirements: We will guide the customer to conduct a continuous no-load test run for at least 8 hours. During this period, we will record the motor current, bearing temperature, reducer temperature and other key parameters every 30 minutes, and keep the data for future reference.
  • Key Monitoring Indicators:We have clearly stipulated that the maximum temperature rise of the bearings should not exceed 40°C, and the maximum temperature should not exceed 70°C; the maximum temperature rise of the reducer should not exceed 45°C - 60°C, and the maximum temperature should not exceed 80°C; the maximum temperature rise of the motor should not exceed 65°C, and the maximum temperature should not exceed 105°C; there should be no abnormal noise or severe vibration during the operation of the equipment.
  • Fault Handling: We will remind the customer that if temperature exceeds the limit, abnormal noise or other problems occur during the test run, they must immediately stop the machine for inspection, eliminate the faults before re-running the test, and strictly prohibit forced operation to cause equipment damage.

 

 Step 9: Load Test Run

  • Loading Procedure:After the no-load test run is completed normally, we will guide the customer to gradually feed a small amount of material to observe the operating status of the equipment. Once the operation is stable, gradually increase the load to the rated capacity. The load test run should last for no less than 2 hours to ensure that the equipment is suitable for the actual production conditions.
  • Performance Optimization:We will assist the customer in monitoring the screening efficiency and processing capacity to ensure they meet the standards. Adjust the uniformity of the feed to ensure that the particle size of the material on the screen meets the customer's production requirements (such as ≤ 50mm), without any blockage or leakage. At the same time, check that the automatic cleaning device is working properly, and there is no material accumulation on the screen to ensure the efficient operation of the equipment.

 

 Step 10: Acceptance And Record Keeping

  • Acceptance Criteria: We will work with the customer to review the equipment technical parameters together, ensuring that the processing capacity, screening efficiency, noise (≤70dB), temperature, etc. all meet the standards. The equipment should operate smoothly without any faults and meet the customer's production requirements before the acceptance process is completed.
  • Record Keeping:We will provide a standardized installation and commissioning record form to guide the customer to fill in detailed information such as basic data, test operation parameters, fault handling situations, and acceptance results. This record will serve as an important basis for us to provide maintenance services to the customer in the future and also facilitate the customer's daily operation and maintenance tracking.

 

 

The installation and commissioning of our Roller Screen cannot be done in an expedited manner. These 10 standardized procedures are the result of our years of service experience and can precisely calibrate the equipment performance, effectively avoiding potential risks during later operation. Standardized operations can enable the equipment to quickly reach the designed production capacity and screening efficiency, extend the lifespan of core components such as the screen shaft and screen plate, and reduce maintenance costs.

The completion of installation and commissioning is not the end. We will continue to provide operation and maintenance support, reminding customers to conduct regular inspections and maintenance on a weekly, monthly, or annual basis. We will also regularly check the lubrication, tightening, and sealing conditions.

If you have any questions during the installation and commissioning, operation, or accessory replacement process, and need professional on-site guidance, please feel free to contact us at any time. Our 24-hour national service hotline will respond promptly, and our professional team will provide precise solutions as soon as possible.